Alhamdulillah, with the blessing & help from mak and abah i managed to complete the project by april, 2014. The delay due to the postponed of the project half way through. Here i post some of the sequences of the jobs done..
Week 1
- Site Clearance
- Demarcation & Setting Out
- Pad Footings Excavation
- Bar bending/tying
Week 2
- Concreting of pad footings
- preparation for ground beams
- concreting of ground beams
- Concreting of ground slab
- Concreting of columns
- Start the brickworks
- This was where the project kiv for a couple of months due to financial hiccup..
-
The Job Resume
- We are using pad footing design instead of pilecap
- Concreting of the ground beams
- Preparation to concreting the ground floor slab.
- Concreting the ground floor slab
- Concreting the columns
- Installing the staging for the second floor slab