Thursday, 2 July 2015

In House Project




End 2013...

Alhamdulillah, with the blessing & help from mak and abah i managed to complete the project by april, 2014.  The delay due to the postponed of the project half way through. Here i post some of the sequences of the jobs done..


Week 1
  •  Site Clearance
  • Demarcation & Setting Out
  • Pad Footings Excavation
  • Bar bending/tying






    Week 2

    • Concreting of pad footings
    • preparation for ground beams
     Week 3
    • concreting of ground beams
     Week 4

    • Concreting of ground slab
     Week 5

    • Concreting of columns
     Week 6

    • Start the brickworks
    Week 7
  • This was where the project kiv for a couple of months due to financial hiccup..
     
     The Job Resume

    • We are using pad footing design instead of pilecap
    •  Concreting of the ground beams

    • Preparation to concreting the ground floor slab.

    • Concreting the ground floor slab


    • Concreting the columns

    • Installing the staging for the second floor slab 
    •  Second floor ready for roof beams

      • Waterproofing works

      • Internal plastering

      • External plastering

      • Roof trusses was installed

      • External plastering
      Skim Coating
      Painting works
      Job Done




No comments:

Post a Comment